Following the successful delivery of the C5A Level 5 Linguistics project for Macquarie University, INAPHASE was invited to tender and subsequently won the refurbishment of existing postgraduate offices for the Biology faculty. The project was delivered whilst the building was still occupied so all noisy work was done out of hours with special attention required to not disturb students during exam times. The scope included demolition, partitions, ceilings, floor coverings, joinery, workstations, loose furniture, whiteboards, electrical, mechanical, fire, hydraulics, security access and signage. We successfully delivered the project in 6 weeks.

CLIENT

Macquarie University Property

VALUE

$650,000 ex GST

AREA

320m²

LOCATION

Building E8A Level 3 - Macquarie University

DURATION

6 weeks